1. Rectangular plot method has been suggested by _________




Answer is C)
Explanation: A simplified rectangular plot method for finding the stability of slopes was suggested by Singh in 1962.


2. The slip circle having the minimum factor of safety is called ___________




Answer is C)
Explanation: A number of trial critical slip circle are chosen against sliding and factor of safety of each is computed. The circle having the minimum factor of safety is the critical slip circle.


3. In Swedish circle method ___________ analysis cases are considered.




Answer is B)
Explanation: In Swedish slip circle method two cases are considered: i) analysis of purely cohesive soil (φu = 0) and ii) analysis of a soil possessing both cohesion and friction (C-φ analysis).


4. When does the critical condition of d/s slope, occur in reservoir?




Answer is A)
Explanation: Critical condition of d/s slope occurs when the reservoir is full and percolation is at its maximum rate.


5. In the rectangular plot method if there are n-slices, the total number of ordinates will be ____________




Answer is A)
Explanation: In the rectangular plot method if there are n-slices, the total number of ordinates will be (n-1), the ordinates at the end of the last strip being zero.


6. Stability of slopes of an earth dam is tested under, which of the following condition?




Answer is A)
Explanation: The stability of slopes of an earth dam is tested under the following conditions: i) Stability of downstream slope during steady seepage ii) Stability of upstream slope during a sudden drawdown iii) Stability of upstream and downstream slopes during and immediately after construction.


7. When a dam is built of impervious compressible soil, water is entrapped in the pore space due to ___________




Answer is B)
Explanation: When a dam is built of relatively impervious compressible soil, excess pore pressure develops in the air and water entrapped in the pore pressure. This is because the soil mass undergoes a change in the soil due to compaction of the dam construction and also due to a down weight.


8. The area of U-diagram in finding stability of D/S slope during steady seepage, can be measured by ___________




Answer is A)
Explanation: The area of U-diagram can be measured with the help of a planimeter, or else the rectangular plot method can be utilized.


9. The magnitude and distribution of pore water pressure on a slip surface can be calculated from ___________




Answer is A)
Explanation: The magnitude and distribution of pore water pressure on a likely slip surface is estimated from pressure net which are developed from the flow net.


10. The pore water pressure at any point on the slip surface is represented by ____________




... Answer is A)
Explanation: The pore water pressure at any point is represented by the piezometric head hw at that point.